United States βΊ Grid βΊ Interconnection queues βΊ North Carolina
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in North Carolina (2024 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project 956754, Stokes County Gas |
940 MW | Withdrawn / abandoned |
| Solar project 956594, Pamlico County Solar Β· Masked |
290 MW | Withdrawn / abandoned |
| Battery storage project 957073, Guilford County Battery storage |
199 MW | Withdrawn / abandoned |
| Solar project 958349, Cumberland County Solar Β· Masked |
157 MW | Withdrawn / abandoned |
| Solar project 962640, Stokes County Solar |
130 MW | Withdrawn / abandoned |
| Solar project 956340, Sampson County Solar Β· Masked |
110 MW | Withdrawn / abandoned |
| Battery storage project 956180, Rockingham County Battery storage |
99.0 MW | Withdrawn / abandoned |
| Solar project 956650, Moore County Solar Β· Masked |
87.0 MW | Withdrawn / abandoned |
| Solar project 962543, Wayne County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 962986, Jones County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 962939, Scotland County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 962788, Pitt County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 961894, Wayne County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 962733, Robeson County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 961752, Bladen County Solar |
79.9 MW | Withdrawn / abandoned |
| Solar project 956958, Nash County Solar |
78.3 MW | Withdrawn / abandoned |
| Solar project 962974, Cumberland County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 957336, Onslow County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 963471, Wayne County Solar |
72.0 MW | Withdrawn / abandoned |
| Solar project 962566, Harnett County Solar |
70.0 MW | Withdrawn / abandoned |
| Battery storage project 957012, Sampson County Battery storage Β· Masked |
60.0 MW | Withdrawn / abandoned |
| Solar project 962795, Vance County Solar |
60.0 MW | Withdrawn / abandoned |
| Solar project 962966, Granville County Solar |
55.0 MW | Withdrawn / abandoned |
| Battery storage project 956518, Cumberland County Battery storage Β· Duke Energy Progress LLC |
50.0 MW | Withdrawn / abandoned |
| Solar project 963103, Duplin County Solar |
49.9 MW | Withdrawn / abandoned |
| Solar project 962964, Hoke County Solar |
45.0 MW | Withdrawn / abandoned |
| Solar project 953801, Robeson County Solar |
44.5 MW | Withdrawn / abandoned |
| Solar project 963470, Randolph County Solar |
40.0 MW | Withdrawn / abandoned |
| Solar project 954798, Cumberland County Solar |
31.6 MW | Withdrawn / abandoned |
| Solar project 963469, Davidson County Solar |
28.8 MW | Withdrawn / abandoned |
| Solar project 958350, Richmond County Solar |
8.2 MW | Withdrawn / abandoned |
| Solar project 957452, Johnston County Solar |
3.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)