United States βΊ Grid βΊ Interconnection queues βΊ North Carolina
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in North Carolina (2019 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project 73054, Davidson County Gas |
1,503 MW | Withdrawn / abandoned |
| Gas project 33170, Person County Gas Β· Duke Energy Progress, LLC |
1,350 MW | Withdrawn / abandoned |
| Gas project 43466, Person County Gas Β· Duke Energy Progress, LLC |
1,350 MW | Withdrawn / abandoned |
| Gas project 30612, Wake County Gas Β· Duke Energy Progress, LLC |
1,350 MW | Withdrawn / abandoned |
| Gas project 43484, Person County Gas Β· Duke Energy Progress, LLC |
1,350 MW | Withdrawn / abandoned |
| Gas project 43510, Person County Gas Β· Duke Energy Progress, LLC |
1,350 MW | Withdrawn / abandoned |
| Gas project 43498, Person County Gas Β· Duke Energy Progress, LLC |
1,350 MW | Withdrawn / abandoned |
| Solar project AF1-236, Tyrrell County Solar |
1,210 MW | Withdrawn / abandoned |
| Gas project 31964, Wilson County Gas Β· Duke Energy Progress, LLC |
803 MW | Withdrawn / abandoned |
| Gas project 31968, Johnston County Gas Β· Duke Energy Progress, LLC |
602 MW | Withdrawn / abandoned |
| Gas project 33182, Person County Gas Β· Duke Energy Progress, LLC |
602 MW | Withdrawn / abandoned |
| Solar project AF1-073, Washington County Solar |
200 MW | Withdrawn / abandoned |
| Solar project AE2-147, Perquimans County Solar Β· Otter Creek Wind Farm, LLC d/b/a Aurora Solar LLC |
150 MW | Withdrawn / abandoned |
| Solar + storage project AF1-312, Rockingham County Solar + storage |
150 MW | Withdrawn / abandoned |
| Solar project AF2-047, Washington County Solar Β· Creswell HWY 64 Solar, LLC |
150 MW | Withdrawn / abandoned |
| Murphy Solar Solar Β· Murphy Solar, LLC |
126 MW | Withdrawn / abandoned |
| Solar project 30708, Nash County Solar |
78.3 MW | Withdrawn / abandoned |
| Battery storage project 44634, Onslow County Battery storage Β· Duke Energy Progress, LLC |
72.0 MW | Withdrawn / abandoned |
| Solar project AE2-037, Bertie County Solar |
71.5 MW | Withdrawn / abandoned |
| Solar project AF1-152, Pasquotank County Solar Β· Otter Creek Wind Farm, LLC d/b/a Aurora Solar LLC |
50.0 MW | Withdrawn / abandoned |
| Solar project AE2-044, Edgecombe County Solar |
40.0 MW | Withdrawn / abandoned |
| Battery storage project AF1-082, Edgecombe County Battery storage |
18.0 MW | Withdrawn / abandoned |
| Battery storage project AE2-207, Edgecombe County Battery storage |
18.0 MW | Withdrawn / abandoned |
| Kruger Energy Hertford Solar |
10.0 MW | Withdrawn / abandoned |
| South Hertford Solar Solar |
5.0 MW | Withdrawn / abandoned |
| Battery storage project 41456, Mecklenburg County Battery storage |
2.8 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)