United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in New York (2012 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown121,080 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn101,963 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Baron Winds
Onshore wind Β· Baron Winds, LLC
239 MWOperating Steuben, NYNYISO Nov 20122022
Baron Winds
Onshore wind Β· Baron Winds, LLC
239 MWOperating NYNYISO Nov 2012
Cassadaga Wind
Onshore wind Β· Cassadaga Wind, LLC
127 MWOperating Chautauqua, NYNYISO Jul 20122020
Cassadaga Wind
Onshore wind Β· Cassadaga Wind, LLC
127 MWOperating NYNYISO Jul 2012
Copenhagen Wind
Onshore wind Β· Copenhagen Wind Farm, LLC
79.9 MWOperating Lewis, NYNYISO Nov 20122019
Copenhagen Wind
Onshore wind Β· Copenhagen Wind Farm, LLC
79.9 MWOperating NYNYISO Nov 2012
Jericho Rise Wind
Onshore wind Β· Jericho Rise Wind Farm, LLC
77.7 MWOperating NYNYISO Dec 2012
Jericho Rise Wind
Onshore wind Β· Jericho Rise Wind Farm, LLC
77.7 MWOperating Franklin, NYNYISO Dec 20122017
Marsh Hill Wind
Onshore wind Β· Invenergy NY LLC
16.2 MWOperating NYNYISO Mar 2012
Marsh Hill Wind
Onshore wind Β· Invenergy NY LLC
16.2 MWOperating Steuben, NYNYISO Mar 20122014
Eagle Creek Hydro
Hydro Β· Eagle Creek Hydro, LLC
0.8 MWOperating Sullivan, NYNYISO Mar 20122014
Eagle Creek Hydro
Hydro Β· Eagle Creek Hydro, LLC
0.8 MWOperating NYNYISO Mar 2012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)