United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in New Mexico (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown81,374 MW
Active in queue1,374 MW8 requests
Agreement signed0.0 MW0 requests
Withdrawn394,318 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
LA300W
Onshore wind
300 MWPaused / redesign Luna, NMWest Mar 2022target 2028
Wind + storage project IA-PNM-2023-08, Guadalupe County
Wind + storage
300 MWIn study Guadalupe, NMWest Dec 2022target 2025
Onshore wind project IA-PNM-2023-01, Cibola County
Onshore wind
250 MWIn study Cibola, NMWest Oct 2022target 2025
Solar + storage project IA-PNM-2023-06, Mckinley County
Solar + storage
199 MWIn study Mckinley, NMWest Dec 2022target 2025
Battery storage project IA-PNM-2022-11, Bernalillo County
Battery storage
100 MWIn study Bernalillo, NMWest Apr 2022target 2024
Solar + storage project IA-PNM-2022-03, Santa Fe County
Solar + storage
100 MWIn study Santa Fe, NMWest Apr 2022target 2025
VS75SB
Solar + storage
75.0 MWPaused / redesign Dona Ana, NMWest Sep 2022target 2026
Battery storage project IA-PNM 2022-10, Sandoval County
Battery storage
50.0 MWIn study Sandoval, NMWest Apr 2022target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)