United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in New Jersey (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown13563 MW
Active in queue563 MW13 requests
Agreement signed546 MW11 requests
Withdrawn352,924 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Woods Landing Energy Storage
Battery storage
250 MWAgreement signed Atlantic, NJPJM Mar 2020target 2030
Two Rivers Storage
Battery storage
150 MWAgreement signed Hudson, NJPJM Mar 2020target 2028
Fenwick Creek Solar
Solar + storage
38.0 MWAgreement signed Atlantic, NJPJM Sep 2020target 2028
Lacey Sand Solar
Solar
19.8 MWAgreement signed Ocean, NJPJM Sep 2020target 2028
Ridge Road Solar Farm
Solar
19.8 MWAgreement signed Hunterdon, NJPJM Sep 2020target 2028
South Combe
Solar
15.4 MWAgreement signed Morris, NJPJM Sep 2020target 2025
Monmouth Solar 1
Solar
15.4 MWAgreement signed Monmouth, NJPJM Sep 2020target 2026
Southern Ocean Waretown Solar
Solar
12.0 MWAgreement signed Ocean, NJPJM Sep 2020target 2028
Washington Solar PH II
Solar
11.0 MWAgreement signed Warren, NJPJM Mar 2020target 2025
Esky Solar Project
Solar
10.0 MWAgreement signed Gloucester, NJPJM Sep 2020target 2025
NJ Land Phase II
Solar
10.0 MWPaused / redesign Burlington, NJPJM Mar 2020target 2025
Barbertown Solar
Solar
7.0 MWPaused / redesign Hunterdon, NJPJM Mar 2020target 2026
Naes
Battery storage
5.0 MWAgreement signed Burlington, NJPJM Sep 2020target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)