United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in New Jersey (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown121,566 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn121,566 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
CPV Keasbey Energy Center
Gas
675 MWWithdrawn / abandoned Middlesex, NJPJM Oct 2013target 2027
Other project Z1-083, Salem County
Other
300 MWWithdrawn / abandoned Salem, NJPJM Oct 2013
Gas project Z1-109, Union County
Gas
208 MWWithdrawn / abandoned Union, NJPJM Oct 2013target 2016
Linden Cogen Uprate
Gas Β· East Coast Power LLC
208 MWWithdrawn / abandoned Union, NJNYISO Mar 2013
Gas project Y3-108, Union County
Gas
110 MWWithdrawn / abandoned Union, NJPJM Apr 2013target 2014
Battery storage project Y3-105, Warren County
Battery storage
20.0 MWWithdrawn / abandoned Warren, NJPJM Apr 2013target 2015
Gas project Y3-047, Essex County
Gas
10.0 MWWithdrawn / abandoned Essex, NJPJM Feb 2013target 2013
Other project Z2-004, Gloucester County
Other
10.0 MWWithdrawn / abandoned Gloucester, NJPJM Nov 2013target 2014
Recovery Road Solar Farm
Solar
7.1 MWWithdrawn / abandoned Burlington, NJPJM Nov 2013target 2018
Camden (Cinnaminson Solar) 26kV
Solar
6.0 MWWithdrawn / abandoned Burlington, NJPJM Jan 2013target 2015
Linden Generating Station
Gas
6.0 MWWithdrawn / abandoned Union, NJPJM Feb 20132015
Solar project Y3-101, Ocean County
Solar
5.7 MWWithdrawn / abandoned Ocean, NJPJM Apr 2013target 2014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)