United States › Grid › Interconnection queues › New Jersey

GAS · PJM

CPV Keasbey Energy Center

CPV Keasbey Energy Center is a 675 MW gas request withdrawn in the PJM interconnection queue, in Middlesex County, New Jersey, connecting to PSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2013 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. ConsentedMar 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Z1-116
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Metuchen 230kV
Location
Middlesex County, New Jersey
Technology
Gas: 675 MW
Total requested
675 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
31 October 2013
Agreement signed
28 March 2019
Proposed online date
January 2027
Withdrawn
October 2023

Location

Marker shows the centre of Middlesex County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Middlesex County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem