πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

BATTERY STORAGE Β· PJM

Battery storage project Y3-105, Warren County

Battery storage project Y3-105, Warren County is a 20.0 MW battery storage request withdrawn in the PJM interconnection queue, in Warren County, New Jersey, connecting to JCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2013 (completed)
  2. Withdrawn / abandonedOct 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Y3-105
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Belvidere-Gilbert-115kV
Location
Warren County, New Jersey
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
30 April 2013
Proposed online date
January 2015
Withdrawn
October 2013

Location

Marker shows the centre of Warren County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Warren County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem