Completed queue projects in New Jersey (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown17226 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn366,519 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

17 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Bayonne Energy Center II
Gas Β· Bayonne Energy Center
129 MWOperating Hudson, NJNYISO Aug 20152019
Atlantic-RedBank 34.5kV Solar
Solar
20.0 MWOperating Monmouth, NJPJM Apr 20152019
Alpha Battery Storage Facility
Battery storage
20.0 MWOperating Warren, NJPJM Mar 20152019
Lakehurst Solar Farm
Solar
9.6 MWOperating Ocean, NJPJM Oct 20152020
Roy Road Battery Storage Facility
Battery storage
8.0 MWOperating Sussex, NJPJM Feb 20152023
Lakewood-Farmingdale Road Storage Facility
Battery storage
7.0 MWOperating Monmouth, NJPJM Feb 20152023
Lumberton Solar
Solar
6.8 MWOperating Burlington, NJPJM Jul 20152016
Nixon Lane Solar
Solar
6.6 MWOperating Middlesex, NJPJM Oct 20152017
Roy Road Battery Storage Facility
Battery storage
6.0 MWOperating Sussex, NJPJM Feb 20152023
Legler Landfill Solar Farm
Solar
2.9 MWOperating Ocean, NJPJM Oct 20152021
Oak Street Landfill Solar Project
Solar
2.3 MWOperating Atlantic, NJPJM May 20152020
West Caldwell Solar
Solar + storage
2.0 MWOperating Essex, NJPJM Jun 20152018
Princeton Hospital NRG Energy Center
Gas
2.0 MWOperating Mercer, NJPJM Feb 20152017
Hopewell Valley Solar
Solar + storage
1.0 MWOperating Mercer, NJPJM Feb 20152015
Gas project AB1-116, Atlantic County
Gas
0.8 MWOperating Atlantic, NJPJM Oct 20152018
Tansboro Road
Gas
0.7 MWOperating Camden, NJPJM Oct 20152018
Cooper Solar
Solar + storage
0.4 MWOperating Camden, NJPJM Sep 20152017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)