United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in New Jersey (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown31264 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn1623,767 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

31 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project X4-005, Middlesex County
Gas
60.0 MWOperating Middlesex, NJPJM Nov 20112015
Newark Energy Center
Gas
35.0 MWOperating Essex, NJPJM Aug 20112015
Eagle Point
Gas
22.9 MWOperating Gloucester, NJPJM Mar 20112012
Howell Solar Farm
Solar
17.0 MWOperating Middlesex, NJPJM Mar 20112014
CHP Belvidere Generation Facility
Gas
11.2 MWOperating Warren, NJPJM Aug 20112013
Frankford Solar Farm
Solar
10.0 MWOperating Sussex, NJPJM Feb 20112016
Old Bridge Solar Farm
Solar
10.0 MWOperating Middlesex, NJPJM Jan 20112018
Hengst Solar Farm
Solar
10.0 MWOperating Warren, NJPJM Jan 20112016
Red Oak
Gas
10.0 MWOperating Middlesex, NJPJM Apr 20112012
Bayonne Cogen
Gas
10.0 MWOperating Hudson, NJPJM Nov 20112013
Hamptons at Pohatcong Solar Farm
Solar
8.0 MWOperating Warren, NJPJM Jan 20112020
North American Solar
Solar
7.0 MWOperating Burlington, NJPJM Jan 20112016
Junction Road Solar Farm
Solar
6.0 MWOperating Hunterdon, NJPJM Jul 20112016
Elmwood
Gas
6.0 MWOperating Bergen, NJPJM May 20112012
Jacobstown III Solar Farm
Solar
5.0 MWOperating Burlington, NJPJM Nov 20112015
Upper Freehold Solar
Solar
5.0 MWOperating Monmouth, NJPJM Apr 20112016
Mill Creek
Solar
3.5 MWOperating Burlington, NJPJM Apr 20112011
Essex County Correctional Facility
Gas
3.0 MWOperating Essex, NJPJM Sep 20112014
Augusta Solar Farm
Solar
3.0 MWOperating Sussex, NJPJM Jan 20112016
Wetteland Solar Farm
Solar
3.0 MWOperating Hunterdon, NJPJM Jan 20112016
Bernards Township Solar Farm
Solar
3.0 MWOperating Somerset, NJPJM Apr 20112016
Owens Corning Solar
Solar
3.0 MWOperating Camden, NJPJM Oct 20112017
Black Rock Solar
Solar
2.4 MWOperating Middlesex, NJPJM Jul 20112012
Summit Associates Solar
Solar
2.0 MWOperating Middlesex, NJPJM Jul 20112011
Skudera Solar Farm
Solar
2.0 MWOperating Monmouth, NJPJM Dec 20112015
Mantua Creek Frequency Regularor
Battery storage
2.0 MWOperating Gloucester, NJPJM May 20112013
Food Bank Solar
Solar
1.0 MWOperating Union, NJPJM Jul 20112012
Hackensack Solar Farm
Solar
1.0 MWOperating Bergen, NJPJM Apr 20112013
Southern Division Headquarters
Solar
0.9 MWOperating Burlington, NJPJM Apr 20112013
Rider University
Solar
0.7 MWOperating Mercer, NJPJM Jan 20112011
Metro Division Headquarters
Solar
0.6 MWOperating Passaic, NJPJM Jan 20112012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)