Summit Associates Solar

Summit Associates Solar is a 2.0 MW solar request built and operating in the PJM interconnection queue, in Middlesex County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Jul 2011 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
X2-089
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Pierson Avenue 13kV
Location
Middlesex County, New Jersey
Technology
Solar: 2.0 MW
Total requested
2.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
29 July 2011
Proposed online date
September 2012
Came online
December 2011

Location

Marker shows the centre of Middlesex County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Middlesex County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem