United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Nevada (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown101,522 MW
Active in queue1,522 MW10 requests
Agreement signed533 MW7 requests
Withdrawn111,145 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project NC5-002, Clark County
Other
499 MWIn study Clark, NVWest May 2017target 2022
Solar + storage project NC5-003, Clark County
Solar + storage
250 MWIn study Clark, NVWest Aug 2017target 2022
Solar + storage project Company HQ, Pershing County
Solar + storage
240 MWPaused / redesign Pershing, NVWest Sep 2017target 2024
Solar project Company IA, Washoe County
Solar
120 MWAgreement signed Washoe, NVWest Dec 2017target 2024
Battery storage project Company HS, Washoe County
Battery storage
100 MWAgreement signed Washoe, NVWest Sep 2017target 2027
Solar project Company HL, Lander County
Solar
100 MWAgreement signed Lander, NVWest Mar 2017target 2023
Solar project Company HP, Lander County
Solar
79.0 MWAgreement signed Lander, NVWest Sep 2017target 2027
Battery storage project Company 155, Clark County
Battery storage
50.0 MWAgreement signed Clark, NVWest Sep 2017target 2023
Geothermal project Company HN, Washoe County
Geothermal
45.0 MWAgreement signed Washoe, NVWest Aug 2017target 2026
Geothermal project Company HU, Churchill County
Geothermal
38.5 MWAgreement signed Churchill, NVWest Sep 2017target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)