United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Nevada (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown275,327 MW
Active in queue14.3 GW40 requests
Agreement signed1,264 MW5 requests
Withdrawn275,327 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

27 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Company PI, Humboldt County
Solar + storage
500 MWWithdrawn / abandoned Humboldt, NVWest Mar 2022target 2029
Solar + storage project Company NN, Storey County
Solar + storage
500 MWWithdrawn / abandoned Storey, NVWest Mar 2022target 2025
Battery storage project Company PJ, Humboldt County
Battery storage
500 MWWithdrawn / abandoned Humboldt, NVWest Mar 2022target 2029
Battery storage project Company 227, Clark County
Battery storage
344 MWWithdrawn / abandoned Clark, NVWest Sep 2022target 2024
Solar + storage project Company 214, Clark County
Solar + storage
300 MWWithdrawn / abandoned Clark, NVWest Mar 2022target 2026
Onshore wind project Company 233, Clark County
Onshore wind
260 MWWithdrawn / abandoned Clark, NVWest Sep 2022target 2026
Solar + storage project Company NI, Churchill County
Solar + storage
250 MWWithdrawn / abandoned Churchill, NVWest Mar 2022target 2025
Solar + storage project Company 229, Clark County
Solar + storage
250 MWWithdrawn / abandoned Clark, NVWest Sep 2022target 2026
Onshore wind project Company MZ, Elko County
Onshore wind
220 MWWithdrawn / abandoned Elko, NVWest Mar 2022target 2026
Solar + storage project Company OD, Lyon County
Solar + storage
200 MWWithdrawn / abandoned Lyon, NVWest Sep 2022target 2026
Battery storage project Company NT, Storey County
Battery storage
200 MWWithdrawn / abandoned Storey, NVWest Sep 2022target 2024
Solar + storage project Company 232, Clark County
Solar + storage
200 MWWithdrawn / abandoned Clark, NVWest Sep 2022target 2026
Solar + storage project Company NK, Lyon County
Solar + storage
200 MWWithdrawn / abandoned Lyon, NVWest Mar 2022target 2026
Solar + storage project Company MQ, Washoe County
Solar + storage
150 MWWithdrawn / abandoned Washoe, NVWest Mar 2022target 2022
Solar + storage project Company 215, Clark County
Solar + storage
150 MWWithdrawn / abandoned Clark, NVWest Mar 2022target 2026
Solar + storage project Company NY, Lander County
Solar + storage
150 MWWithdrawn / abandoned Lander, NVWest Sep 2022target 2024
Wind + storage project Company MR, Lyon County
Wind + storage
150 MWWithdrawn / abandoned Lyon, NVWest Mar 2022target 2026
Gas project Company NM, Storey County
Gas
128 MWWithdrawn / abandoned Storey, NVWest Mar 2022target 2027
Solar + storage project Company NE, Humbolt County
Solar + storage
100 MWWithdrawn / abandoned Humbolt, NVWest Mar 2022target 2025
Solar + storage project Company NF, Humbolt County
Solar + storage
100 MWWithdrawn / abandoned Humbolt, NVWest Mar 2022target 2025
Solar + storage project Company OE, Humboldt County
Solar + storage
100 MWWithdrawn / abandoned Humboldt, NVWest Nov 2022target 2026
Solar + storage project Company NG, Humboldt County
Solar + storage
100 MWWithdrawn / abandoned Humboldt, NVWest Mar 2022target 2025
Solar + storage project Company MO, Nye County
Solar + storage
100 MWWithdrawn / abandoned Nye, NVWest Feb 2022target 2023
Battery storage project Company MS, Carson City County
Battery storage
100 MWWithdrawn / abandoned Carson City, NVWest Mar 2022target 2026
Solar + storage project Company OC, Lander County
Solar + storage
30.0 MWWithdrawn / abandoned Lander, NVWest Sep 2022target 2026
Geothermal project Company MP, Churchill County
Geothermal
25.0 MWWithdrawn / abandoned Churchill, NVWest Mar 2022target 2022
Battery storage project Company 223, Clark County
Battery storage
20.0 MWWithdrawn / abandoned Clark, NVWest Jun 2022target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)