πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Nevada (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown211,892 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn211,892 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

21 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Hidden Hills Ranch
Solar
540 MWWithdrawn / abandoned Nye, NVCAISO Mar 2011target 2014
Sandy Valley Phase I Segs (Fka Pahrump Valley Segs)
Solar
270 MWWithdrawn / abandoned Clark, NVCAISO Mar 2011target 2016
Other project Company FK, White Pine County
Other
200 MWWithdrawn / abandoned White Pine, NVWest Apr 2011target 2015
Solar project Company 110, Clark County
Solar
150 MWWithdrawn / abandoned Clark, NVWest Jul 2011target 2015
Solar project Company 113, Clark County
Solar
150 MWWithdrawn / abandoned Clark, NVWest Nov 2011target 2015
Solar project Company 102, Clark County
Solar
100 MWWithdrawn / abandoned Clark, NVWest Jan 2011target 2014
Onshore wind project Company 105, Clark County
Onshore wind
85.5 MWWithdrawn / abandoned Clark, NVWest Feb 2011target 2015
Coyote Canyon
Geothermal
70.0 MWWithdrawn / abandoned Churchill, NVCAISO Mar 2011target 2013
Solar project Company 111, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, NVWest Sep 2011target 2014
Dixie-Comstock Geothermal Project
Geothermal
38.0 MWWithdrawn / abandoned Churchill, NVCAISO Mar 2011target 2014
Edwards Creek Geothermal Project
Geothermal
38.0 MWWithdrawn / abandoned Churchill, NVCAISO Mar 2011target 2014
Tungsten Mountain Geothermal Project
Geothermal
38.0 MWWithdrawn / abandoned Churchill, NVCAISO Mar 2011target 2013
Deadhorse Wells Geothermal Project
Geothermal
27.0 MWWithdrawn / abandoned Mineral, NVCAISO Mar 2011target 2013
Solar project Company 100, Clark County
Solar
20.0 MWWithdrawn / abandoned Clark, NVWest Jan 2011target 2012
Solar project Company 103, Clark County
Solar
20.0 MWWithdrawn / abandoned Clark, NVWest Jan 2011target 2012
Solar project Company 104, Clark County
Solar
20.0 MWWithdrawn / abandoned Clark, NVWest Jan 2011target 2012
Solar project Company 101, Clark County
Solar
20.0 MWWithdrawn / abandoned Clark, NVWest Jan 2011target 2012
Solar project Company 112, Clark County
Solar
20.0 MWWithdrawn / abandoned Clark, NVWest Sep 2011target 2013
Solar project Company 109, Clark County
Solar
15.0 MWWithdrawn / abandoned Clark, NVWest May 2011target 2013
Solar project Company 107, Clark County
Solar
10.0 MWWithdrawn / abandoned Clark, NVWest Apr 2011target 2013
Solar project Company 108, Clark County
Solar
10.0 MWWithdrawn / abandoned Clark, NVWest May 2011target 2013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)