United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Nevada (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7707 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn161,645 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project Company 144, Clark County
Solar
300 MWOperating Clark, NVWest Mar 2015target 2018
Solar + storage project Company GU, Washoe County
Solar + storage
200 MWOperating Washoe, NVWest Sep 2015target 2021
Solar project Company GV, Lander County
Solar
101 MWOperating Lander, NVWest Sep 2015target 2016
Solar project Company GR, Washoe County
Solar
60.0 MWOperating Washoe, NVWest Mar 2015target 2016
Solar project Company GK, Churchill County
Solar
20.0 MWOperating Churchill, NVWest Mar 2015target 2018
Geothermal project Company GX, Lander County
Geothermal
20.0 MWOperating Lander, NVWest Sep 2015target 2016
Geothermal project Company GW, Mineral County
Geothermal
6.0 MWOperating Mineral, NVWest Sep 2015target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)