United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Nevada (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown51,264 MW
Active in queue14.3 GW40 requests
Agreement signed1,264 MW5 requests
Withdrawn275,327 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Company MW, White Pine County
Solar + storage
400 MWAgreement signed White Pine, NVWest Mar 2022target 2030
Gas project Company 230, Clark County
Gas
222 MWAgreement signed Clark, NVWest Sep 2022target 2024
Gas project Company 231, Clark County
Gas
222 MWAgreement signed Clark, NVWest Sep 2022target 2024
Battery storage project Company 211, Clark County
Battery storage
220 MWAgreement signed Clark, NVWest Jan 2022target 2029
Battery storage project Company NJ, Storey County
Battery storage
200 MWAgreement signed Storey, NVWest Mar 2022target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)