Interconnection queue in Nebraska (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown81,704 MW
Active in queue1,704 MW8 requests
Agreement signed1,204 MW5 requests
Withdrawn299,654 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2018-043, Burt County
Solar
500 MWAgreement signed Burt, NESPP May 2018target 2028
Onshore wind project GEN-2018-125, Lancaster County
Onshore wind
231 MWAgreement signed Lancaster, NESPP Nov 2018target 2031
Solar project GEN-2018-131, Pierce County
Solar
221 MWAgreement signed Pierce, NESPP Nov 2018target 2031
Solar project GEN-2018-132, Pierce County
Solar
202 MWAgreement signed Pierce, NESPP Nov 2018target 2026
Battery storage project GEN-2018-025, Washington County
Battery storage
200 MWPaused / redesign Washington, NESPP May 2018target 2028
Battery storage project GEN-2018-033, Cass County
Battery storage
200 MWPaused / redesign Cass, NESPP May 2018target 2029
Battery storage project GEN-2018-037, Douglas County
Battery storage
100 MWPaused / redesign Douglas, NESPP May 2018target 2030
Onshore wind project GEN-2018-060, Webster County
Onshore wind
50.0 MWAgreement signed Webster, NESPP May 2018target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)