United States β€Ί Grid β€Ί Interconnection queues β€Ί Nebraska

OCTARY USA Β· INTERCONNECTION QUEUES

Other interconnection queue in Nebraska

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5587 MW
Active in queue587 MW5 requests
Agreement signed21.9 MW1 requests
Withdrawn146.0 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project GEN-2025-SR24, Washington County
Other
200 MWIn study Washington, NESPP Jun 2025target 2028
Other project GEN-2025-SR26, Cass County
Other
200 MWIn study Cass, NESPP Jun 2025target 2029
Other project GEN-2025-SR20, Douglas County
Other
100 MWIn study Douglas, NESPP Jun 2025target 2030
Other project GEN-2024-231, Richardson County
Other
65.0 MWIn study Richardson, NESPP Mar 2025target 2029
Other project GEN-2023-SR1, Brown County
Other
21.9 MWAgreement signed Brown, NESPP Dec 20222024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)