United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Mississippi (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2196 MW
Active in queue196 MW2 requests
Agreement signed0.0 MW0 requests
Withdrawn264,604 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J962, Desoto County
Solar
100 MWUnder construction Desoto, MSMISO Mar 20182024
Solar project J1144, Covington County
Solar
96.0 MWUnder construction Covington, MSMISO Mar 2018target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)