United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

OCTARY USA Β· INTERCONNECTION QUEUES

Onshore wind interconnection queue in Mississippi

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5947 MW
Active in queue947 MW5 requests
Agreement signed0.0 MW0 requests
Withdrawn71,987 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J3623, Sunflower County
Onshore wind
350 MWIn study Sunflower, MSMISO Apr 2024target 2028
Onshore wind project J866, Tunica County
Onshore wind
200 MWUnder construction Tunica, MSMISO Jun 20172024
Onshore wind project J2571, Tunica County
Onshore wind
177 MWIn study Tunica, MSMISO Sep 2022target 2024
Onshore wind project J3900, Sunflower County
Onshore wind
163 MWIn study Sunflower, MSMISO Dec 2024target 2030
Onshore wind project J3592, Sunflower County
Onshore wind
57.0 MWIn study Sunflower, MSMISO Apr 2024target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)