United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

OCTARY USA Β· INTERCONNECTION QUEUES

Gas interconnection queue in Mississippi

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown63,344 MW
Active in queue3,344 MW6 requests
Agreement signed0.0 MW0 requests
Withdrawn2011.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J1813, Desoto County
Gas
1,005 MWIn study Desoto, MSMISO Jul 2022target 2002
Lakeover CCCT
Gas Β· Entergy Mississippi, LLC
820 MWIn study Hinds, MSMISO Aug 2025target 2028
Vicksburg CCCT
Gas Β· Entergy Mississippi, LLC
820 MWIn study Warren, MSMISO Aug 2025target 2027
Gas project 569, Lowndes County
Gas
620 MWIn study Lowndes, MSSoutheast Jun 2023target 2026
Gas project 656, Benton County
Gas
54.0 MWIn study Benton, MSSoutheast Oct 2024target 2030
Gas project 25-IC-1316, Kemper County
Gas
25.0 MWIn study Kemper, MSSoutheast Apr 2025target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)