πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Minnesota (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3155 MW
Active in queue155 MW3 requests
Agreement signed105 MW2 requests
Withdrawn263,748 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J569, Rock County
Onshore wind
100 MWAgreement signed Rock, MNMISO May 20162022
Solar project J718, Fillmore County
Solar
50.0 MWUnder construction Fillmore, MNMISO Sep 20162024
Wind + storage project R101, Red Lake County
Wind + storage
4.6 MWAgreement signed Red Lake, MNMISO Mar 20162020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)