United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Michigan (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6780 MW
Active in queue780 MW6 requests
Agreement signed200 MW1 requests
Withdrawn335,843 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J984, Gratiot County
Onshore wind
200 MWUnder construction Gratiot, MIMISO Mar 20182023
Solar project J1062, Washtenaw County
Solar
200 MWAgreement signed Washtenaw, MIMISO Mar 2018target 2023
Wingstem Solar Energy Farm
Solar
150 MWPaused / redesign Cass, MIPJM Sep 2018target 2025
Solar project J1071, Oceana County
Solar
100 MWUnder construction Oceana, MIMISO Mar 2018target 2021
Solar project J996, Lenawee County
Solar
80.0 MWUnder construction Lenawee, MIMISO Mar 2018target 2022
Solar project J1172, Genesee County
Solar
50.0 MWUnder construction Genesee, MIMISO Mar 2018target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)