United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

OCTARY USA Β· INTERCONNECTION QUEUES

Gas interconnection queue in Michigan

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown149,742 MW
Active in queue9,742 MW14 requests
Agreement signed56.4 MW3 requests
Withdrawn4517.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

14 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J4024, Monroe County
Gas
1,499 MWIn study Monroe, MIMISO May 2025target 2030
Gas project J4025, Monroe County
Gas
1,499 MWIn study Monroe, MIMISO May 2025target 2030
Gas project J3799, Livingston County
Gas
1,452 MWIn study Livingston, MIMISO Apr 2024target 2030
Gas project J3922, Branch County
Gas
1,445 MWIn study Branch, MIMISO Mar 2025target 2030
Gas project J3923, Washtenaw County
Gas
1,414 MWIn study Washtenaw, MIMISO Feb 2025target 2030
Gas project J3935, Genesee County
Gas
1,268 MWIn study Genesee, MIMISO Feb 2025target 2030
Gas project J4159, Ottawa County
Gas
664 MWIn study Ottawa, MIMISO Aug 2025target 2028
Gas project J4160, Ottawa County
Gas
425 MWIn study Ottawa, MIMISO Aug 2025target 2026
Gas project J1798, Wayne County
Gas
25.0 MWAgreement signed Wayne, MIMISO Jun 2020target 2023
Gas project J1262, Wayne County
Gas
25.0 MWAgreement signed Wayne, MIMISO Apr 2019target 2022
Gas project J2969, Kalkaska County
Gas
13.4 MWIn study Kalkaska, MIMISO Sep 2022target 2002
Gas project J571, Kalamazoo County
Gas
6.4 MWAgreement signed Kalamazoo, MIMISO May 2016target 2018
Gas project J3756, Marquette County
Gas
4.2 MWIn study Marquette, MIMISO Apr 2024target 2019
Gas project J3800, Baraga County
Gas
1.8 MWIn study Baraga, MIMISO Apr 2024target 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)