United States β€Ί Grid β€Ί Interconnection queues β€Ί Maryland

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Maryland (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown16486 MW
Active in queue257 MW6 requests
Agreement signed80.0 MW1 requests
Withdrawn16486 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

16 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AF1-037, Baltimore County
Battery storage
200 MWWithdrawn / abandoned Baltimore, MDPJM May 2019target 2021
Solar project AE2-209, Dorchester County
Solar
56.0 MWWithdrawn / abandoned Dorchester, MDPJM Mar 2019target 2021
Solar project AF1-044, Allegany County
Solar
45.0 MWWithdrawn / abandoned Allegany, MDPJM Jun 2019target 2021
Crockett Solar Project
Solar
44.0 MWWithdrawn / abandoned Talbot, MDPJM Feb 2019target 2026
Solar project AF1-121, Prince George's County
Solar
20.0 MWWithdrawn / abandoned Prince George's, MDPJM Sep 2019target 2021
Solar project AF1-284, Garrett County
Solar
20.0 MWWithdrawn / abandoned Garrett, MDPJM Sep 2019target 2021
Solar project AE2-286, Dorchester County
Solar
19.5 MWWithdrawn / abandoned Dorchester, MDPJM Mar 2019target 2019
Solar project AF1-004, Charles County
Solar
16.8 MWWithdrawn / abandoned Charles, MDPJM Apr 2019target 2021
Crockett Solar Project
Solar
15.0 MWWithdrawn / abandoned Talbot, MDPJM Apr 2019target 2026
Sand Flat Road Solar Project
Solar
13.8 MWWithdrawn / abandoned Garrett, MDPJM Apr 2019target 2023
Battery storage project AF1-269, Dorchester County
Battery storage
11.0 MWWithdrawn / abandoned Dorchester, MDPJM Sep 2019target 2022
Battery storage project AF1-244, Somerset County
Battery storage
8.0 MWWithdrawn / abandoned Somerset, MDPJM Sep 2019target 2020
Battery storage project AE2-301, Somerset County
Battery storage
5.5 MWWithdrawn / abandoned Somerset, MDPJM Mar 2019target 2021
Solar project AE2-336, Prince George's County
Solar
4.6 MWWithdrawn / abandoned Prince George's, MDPJM Mar 2019target 2020
Solar project AE2-070, Howard County
Solar
4.0 MWWithdrawn / abandoned Howard, MDPJM Feb 2019target 2020
Solar project AE2-337, Prince George's County
Solar
2.4 MWWithdrawn / abandoned Prince George's, MDPJM Mar 2019target 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)