Completed queue projects in Maryland (2012 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown51,587 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn13201 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Wildcat Point
Gas
834 MWOperating Cecil, MDPJM Apr 20122017
Keys Energy Center
Gas
736 MWOperating Prince George's, MDPJM Jan 20122018
Wye Mills Solar Site
Solar
10.0 MWOperating Talbot, MDPJM Apr 20122016
Eastern Landfill Gas
Other
4.0 MWOperating Baltimore, MDPJM Oct 20122016
Constellation Solar Maryland II, LLC Solar Facility
Solar
3.4 MWOperating Dorchester, MDPJM Apr 20122015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)