Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6417 MW
Active in queue417 MW6 requests
Agreement signed417 MW6 requests
Withdrawn11387 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Green Apple Solar
Solar
179 MWAgreement signed Androscoggin, MEISO-NE Feb 2021target 2027
Solar
Solar
165 MWAgreement signed Somerset, MEISO-NE Feb 2021target 2029
Solar Knox
Solar
33.5 MWAgreement signed Knox, MEISO-NE Oct 2021target 2027
Turner Meadow Solar
Solar
19.8 MWAgreement signed Androscoggin, MEISO-NE Jun 2021target 2026
Twin Energy Wind
Onshore wind
18.3 MWAgreement signed Oxford, MEISO-NE Oct 2021target 2026
Roxbury Solar
Solar
2.0 MWAgreement signed Oxford, MEISO-NE Oct 2021target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)