Requests shown11976 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn11976 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Wind
Onshore wind
245 MWWithdrawn / abandoned Franklin, MEISO-NE Nov 2015target 2019
Wind
Onshore wind
216 MWWithdrawn / abandoned Franklin, MEISO-NE Nov 2015target 2019
Solar
Solar
152 MWWithdrawn / abandoned Somerset, MEISO-NE Nov 2015target 2019
Wind
Onshore wind
113 MWWithdrawn / abandoned Franklin, MEISO-NE Nov 2015target 2019
Wind Farm
Onshore wind
79.2 MWWithdrawn / abandoned Somerset, MEISO-NE Aug 2015target 2019
Battery Storage
Wind + storage
52.3 MWWithdrawn / abandoned Franklin, MEISO-NE Nov 2015target 2019
Wind farm
Onshore wind
39.6 MWWithdrawn / abandoned Oxford, MEISO-NE Aug 2015target 2019
Combined Cycle Uprate
Gas
30.0 MWWithdrawn / abandoned Penobscot, MEISO-NE Feb 2015target 2018
Battery Storage
Wind + storage
25.1 MWWithdrawn / abandoned Franklin, MEISO-NE Nov 2015target 2019
Solar
Solar
19.9 MWWithdrawn / abandoned Franklin, MEISO-NE Jun 2015target 2016
Wind uprate
Onshore wind
2.9 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2015target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)