United States β€Ί Grid β€Ί Interconnection queues β€Ί Louisiana

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Louisiana (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown143,598 MW
Active in queue3,598 MW14 requests
Agreement signed0.0 MW0 requests
Withdrawn4510.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

14 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Replacing 464.5 MW Steam/Gas with 97.8 MW Steam; DOW Chem
Gas
1,232 MWIn study Iberville, LAMISO May 2024target 2025
Solar + storage project J3591, St. Helena Parish County
Solar + storage
400 MWIn study St. Helena Parish, LAMISO Apr 2024target 2028
Battery storage project J3840, St. Landry Parish County
Battery storage
300 MWIn study St. Landry Parish, LAMISO Dec 2024target 2030
Solar project J3454, Morehouse Parish County
Solar
300 MWIn study Morehouse Parish, LAMISO Apr 2024target 2028
Solar project J3479, Rapides Parish County
Solar
225 MWIn study Rapides Parish, LAMISO Apr 2024target 2027
Solar project J3601, Morehouse Parish County
Solar
200 MWIn study Morehouse Parish, LAMISO Apr 2024target 2028
Onshore wind project J3368, St. Landry Parish County
Onshore wind
200 MWIn study St. Landry Parish, LAMISO Apr 2024target 2028
Onshore wind project J3394, St. Landry Parish County
Onshore wind
156 MWIn study St. Landry Parish, LAMISO Apr 2024target 2027
Nuclear project J3815, St. Charles Parish County
Nuclear
153 MWIn study St. Charles Parish, LAMISO Jun 2024target 2026
Solar project J3781, Jefferson Davis Parish County
Solar
150 MWIn study Jefferson Davis Parish, LAMISO Apr 2024target 2027
Solar project J3914, Jefferson Davis Parish County
Solar
85.0 MWIn study Jefferson Davis Parish, LAMISO Oct 2024target 2030
Solar project J3988, Morehouse Parish County
Solar
85.0 MWIn study Morehouse Parish, LAMISO Oct 2024target 2030
Solar + storage project J3630, East Feliciana Parish County
Solar + storage
77.0 MWIn study East Feliciana Parish, LAMISO Apr 2024target 2028
Solar + storage project GEN-2024-044, Caddo Parish County
Solar + storage
36.0 MWIn study Caddo Parish, LASPP Oct 2024target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)