πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Louisiana

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Louisiana (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown118,695 MW
Active in queue19.7 GW43 requests
Agreement signed0.0 MW0 requests
Withdrawn118,695 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project APP-100096
Gas
1,640 MWWithdrawn / abandoned LAMISO Aug 2025
Gas project APP-100103
Gas
1,640 MWWithdrawn / abandoned LAMISO Aug 2025
Gas project J4022, Ouachita Parish County
Gas
1,509 MWWithdrawn / abandoned Ouachita Parish, LAMISO May 2025target 2030
Gas project J4109, Iberville Parish County
Gas
1,300 MWWithdrawn / abandoned Iberville Parish, LAMISO Oct 2025target 2030
Gas project APP-100016
Gas
770 MWWithdrawn / abandoned LAMISO Aug 2025
Gas project J4166, Iberville Parish County
Gas
710 MWWithdrawn / abandoned Iberville Parish, LAMISO Sep 2025target 2029
Gas project J4141, Morehouse Parish County
Gas
650 MWWithdrawn / abandoned Morehouse Parish, LAMISO Oct 2025target 2030
Solar project J3885, Morehouse Parish County
Solar
200 MWWithdrawn / abandoned Morehouse Parish, LAMISO Feb 2025target 2030
Battery storage project J4108, Webster Parish County
Battery storage
150 MWWithdrawn / abandoned Webster Parish, LAMISO Oct 2025target 2030
Solar project J4156, Ouachita Parish County
Solar
93.0 MWWithdrawn / abandoned Ouachita Parish, LAMISO Oct 2025target 2029
Gas project GEN-2024-126, Caddo Parish County
Gas
32.7 MWWithdrawn / abandoned Caddo Parish, LASPP Mar 2025target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)