United States βΊ Grid βΊ Interconnection queues βΊ Louisiana
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Louisiana (2025 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project APP-100096 Gas |
1,640 MW | Withdrawn / abandoned |
| Gas project APP-100103 Gas |
1,640 MW | Withdrawn / abandoned |
| Gas project J4022, Ouachita Parish County Gas |
1,509 MW | Withdrawn / abandoned |
| Gas project J4109, Iberville Parish County Gas |
1,300 MW | Withdrawn / abandoned |
| Gas project APP-100016 Gas |
770 MW | Withdrawn / abandoned |
| Gas project J4166, Iberville Parish County Gas |
710 MW | Withdrawn / abandoned |
| Gas project J4141, Morehouse Parish County Gas |
650 MW | Withdrawn / abandoned |
| Solar project J3885, Morehouse Parish County Solar |
200 MW | Withdrawn / abandoned |
| Battery storage project J4108, Webster Parish County Battery storage |
150 MW | Withdrawn / abandoned |
| Solar project J4156, Ouachita Parish County Solar |
93.0 MW | Withdrawn / abandoned |
| Gas project GEN-2024-126, Caddo Parish County Gas |
32.7 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)