Projects with signed interconnection agreements in Kansas (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown61,307 MW
Active in queue4,490 MW18 requests
Agreement signed1,307 MW6 requests
Withdrawn101,245 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2021-005, Saline County
Battery storage
350 MWAgreement signed Saline, KSSPP May 2021target 2030
Solar project GEN-2021-023, Grant County
Solar
306 MWAgreement signed Grant, KSSPP May 2021target 2030
Onshore wind project GEN-2021-056, Harper County
Onshore wind
300 MWAgreement signed Harper, KSSPP Apr 2021target 2030
Solar project GEN-2021-101, Douglas County
Solar
159 MWAgreement signed Douglas, KSSPP May 2021target 2027
Battery storage project GEN-2021-103, Johnson County
Battery storage
150 MWAgreement signed Johnson, KSSPP May 2021target 2030
Solar project GEN-2021-SR8, Harper County
Solar
42.0 MWAgreement signed Harper, KSSPP May 20212023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)