Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2255 MW
Active in queue255 MW2 requests
Agreement signed0.0 MW0 requests
Withdrawn111,051 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1520, Worth County
Solar
135 MWUnder construction Worth, IAMISO Jun 2020target 2027
Onshore wind project J1769, Howard County
Onshore wind
120 MWIn study Howard, IAMISO Jun 2020target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)