πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Iowa (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown62,762 MW
Active in queue10.3 GW35 requests
Agreement signed0.0 MW0 requests
Withdrawn62,762 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project E0025, Linn County
Gas Β· Interstate Power and Light Company (IPL)
987 MWWithdrawn / abandoned Linn, IAMISO Aug 2025target 2028
Linn County Generating Facility
Nuclear Β· NextEra Energy Resources Development, LLC
676 MWWithdrawn / abandoned Linn, IAMISO Aug 2025target 2028
Solar project J3998, Cerro Gordo County
Solar
450 MWWithdrawn / abandoned Cerro Gordo, IAMISO Feb 2025target 2030
Onshore wind project J3920, Clay County
Onshore wind
300 MWWithdrawn / abandoned Clay, IAMISO Mar 2025target 2030
Solar project J3933, Franklin County
Solar
200 MWWithdrawn / abandoned Franklin, IAMISO Feb 2025target 2028
Solar project J3921, Jasper County
Solar
150 MWWithdrawn / abandoned Jasper, IAMISO Mar 2025target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)