πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Iowa

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown181,860 MW
Active in queue23.9 GW123 requests
Agreement signed1,860 MW18 requests
Withdrawn29566.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

18 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J982, Dickinson County
Onshore wind
300 MWAgreement signed Dickinson, IAMISO Mar 2018target 2024
Onshore wind project J1432, Clinton County
Onshore wind
250 MWAgreement signed Clinton, IAMISO Apr 2019target 2025
Solar project J1218, Muscatine County
Solar
200 MWAgreement signed Muscatine, IAMISO Apr 2019target 2026
Solar project J1190, Clinton County
Solar
200 MWAgreement signed Clinton, IAMISO Jan 2019target 2025
Onshore wind project GEN-2017-222, Crawford County
Onshore wind
180 MWAgreement signed Crawford, IASPP Nov 2017target 2027
Onshore wind project J1175, Worth County
Onshore wind
165 MWAgreement signed Worth, IAMISO Mar 2018target 2024
Solar project J1313, Greene County
Solar
100 MWAgreement signed Greene, IAMISO Apr 2019target 2025
Solar project J524, Webster County
Solar
100 MWAgreement signed Webster, IAMISO Nov 20152022
Onshore wind project GEN-2018-074, Crawford County
Onshore wind
72.0 MWAgreement signed Crawford, IASPP Oct 2018target 2028
Gas project J514, Marshall County
Gas
65.0 MWAgreement signed Marshall, IAMISO Nov 2015target 2017
Battery storage project J1477, Scott County
Battery storage
50.0 MWAgreement signed Scott, IAMISO Apr 2019target 2024
Battery storage project J1229, Muscatine County
Battery storage
50.0 MWAgreement signed Muscatine, IAMISO Apr 2019target 2026
Solar project J1135, Des Moines County
Solar
50.0 MWAgreement signed Des Moines, IAMISO Mar 2018target 2024
Solar project J504, Linn County
Solar
50.0 MWAgreement signed Linn, IAMISO Nov 20152024
Gas project GEN-2019-019, Woodbury County
Gas
15.2 MWAgreement signed Woodbury, IASPP Apr 20192022
Other project J963, Cedar County
Other
9.0 MWAgreement signed Cedar, IAMISO Mar 2018target 2017
Other project J953, Johnson County
Other
2.0 MWAgreement signed Johnson, IAMISO Mar 2018target 2006
Solar project J954, Johnson County
Solar
1.4 MWAgreement signed Johnson, IAMISO Mar 2018target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)