Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6989 MW
Active in queue989 MW6 requests
Agreement signed350 MW2 requests
Withdrawn214,890 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J829, Sullivan County
Solar
250 MWUnder construction Sullivan, INMISO Jun 2017target 2022
Trade Post Solar Energy Center
Solar
200 MWAgreement signed Sullivan, INPJM Mar 2017target 2026
Solar project J805, Shelby County
Solar
199 MWUnder construction Shelby, INMISO Jun 2017target 2022
Riverstart Solar Park IV
Solar
150 MWAgreement signed Randolph, INPJM Sep 2017target 2025
Solar project J903, Henry County
Solar
100 MWUnder construction Henry, INMISO Jun 2017target 2023
Solar project J847, Jasper County
Solar
90.0 MWUnder construction Jasper, INMISO Jun 20172023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)