United States βΊ Grid βΊ Interconnection queues βΊ Illinois
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Illinois (2017 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project AD1-133, Grundy County Solar |
300 MW | Withdrawn / abandoned |
| Onshore wind project AD1-112, Kankakee County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J835, Morgan County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J872, Macon County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project AD1-064, Dekalb County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J467, Douglas County Onshore wind |
102 MW | Withdrawn / abandoned |
| Solar project AD1-098, Lee County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J884, Mclean County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J920, Pulaski County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AC2-173, Winnebago County Solar |
90.0 MW | Withdrawn / abandoned |
| Solar project AD1-126, Dekalb County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project AD1-117, Ogle County Solar |
78.0 MW | Withdrawn / abandoned |
| Onshore wind project J887, Knox County Onshore wind |
75.0 MW | Withdrawn / abandoned |
| Solar project AD1-031, Henry County Solar |
70.0 MW | Withdrawn / abandoned |
| Solar project J797, Washington County Solar |
70.0 MW | Withdrawn / abandoned |
| Solar project J795, Gallatin County Solar |
69.0 MW | Withdrawn / abandoned |
| Solar project AD1-024, Kankakee County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project J881, Jasper County Solar |
45.0 MW | Withdrawn / abandoned |
| Solar project AC2-166, Dekalb County Solar |
40.0 MW | Withdrawn / abandoned |
| Solar project J854, Randolph County Solar |
30.0 MW | Withdrawn / abandoned |
| Solar project AC2-147, Ogle County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AC2-151, Grundy County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AC2-150, Lee County Solar |
20.0 MW | Withdrawn / abandoned |
| Marengo Solar, LLC Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AC2-156, Dekalb County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AD1-116, Lasalle County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AD2-024, Mchenry County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AC2-148, Lee County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AC2-149, Dekalb County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AD1-096, Ogle County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AD1-150, Kankakee County Battery storage |
19.9 MW | Withdrawn / abandoned |
| Solar project J882, Montgomery County Solar |
15.0 MW | Withdrawn / abandoned |
| Cherry Valley Solar Project, LLC Solar |
12.5 MW | Withdrawn / abandoned |
| Solar project AC2-153, Dekalb County Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project AC2-152, Livingston County Solar |
10.0 MW | Withdrawn / abandoned |
| 0 Battery storage |
1.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)