SOLAR Β· MISO

Solar project J795, Gallatin County

Solar project J795, Gallatin County is a 69.0 MW solar request withdrawn in the MISO interconnection queue, in Gallatin County, Illinois, connecting to Southern Illinois Power Cooperative.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedJan 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J795
Grid region
MISO (Midcontinent)
Utility / transmission owner
Southern Illinois Power Cooperative
Connection point (POI)
Gallatin Junction 161 kV Substation
Location
Gallatin County, Illinois
Technology
Solar: 69.0 MW
Total requested
69.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 June 2017
Proposed online date
September 2019
Withdrawn
January 2019

Location

Marker shows the centre of Gallatin County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem