Interconnection queue in Idaho (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6861 MW
Active in queue861 MW6 requests
Agreement signed421 MW3 requests
Withdrawn226,141 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 573, Power County
Solar + storage Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Power, IDWest Nov 2019target 2027
Solar + storage project 551, Elmore County
Solar + storage Β· Bennett Solar B LLC
240 MWPaused / redesign Elmore, IDWest Apr 2019target 2026
Solar project 558, Jerome County
Solar Β· Cat Creek Energy, LLC
120 MWAgreement signed Jerome, IDWest May 2019target 2026
Solar + storage project 100, Benewah County
Solar + storage
100 MWIn study Benewah, IDWest Sep 2019target 2021
Solar + storage project 97, Nez Perce County
Solar + storage
100 MWPaused / redesign Nez Perce, IDWest Jun 2019target 2025
Hydro project 1186, Bannock County
Hydro Β· Commercial Energy Management, Inc.
0.9 MWAgreement signed Bannock, IDWest Oct 2019target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)