πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

OCTARY USA Β· INTERCONNECTION QUEUES

Solar interconnection queue in Idaho

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6866 MW
Active in queue866 MW6 requests
Agreement signed394 MW3 requests
Withdrawn997,387 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 737, Bingham County
Solar
280 MWIn study Bingham, IDWest Sep 2023target 2027
Solar project 636, Elmore County
Solar Β· Soles Rest Solar LLC
149 MWAgreement signed Elmore, IDWest Feb 2022target 2028
Solar project 588, Ada County
Solar Β· PVS 2, LLC
125 MWAgreement signed Ada, IDWest Sep 2020target 2026
Solar project 790, Washington County
Solar
122 MWIn study Washington, IDWest Apr 2025target 2030
Solar project 558, Jerome County
Solar Β· Cat Creek Energy, LLC
120 MWAgreement signed Jerome, IDWest May 2019target 2026
Solar project 787, Elmore County
Solar
70.0 MWIn study Elmore, IDWest Apr 2025target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)