Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown549,728 MW
Active in queue2,109 MW12 requests
Agreement signed200 MW2 requests
Withdrawn549,728 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

54 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Wind + storage project 726, Owyhee County
Wind + storage
529 MWWithdrawn / abandoned Owyhee, IDWest Jun 2023target 2027
Other project 707, Elmore County
Other
500 MWWithdrawn / abandoned Elmore, IDWest Mar 2023
Wind + storage project 714, Owyhee County
Wind + storage
330 MWWithdrawn / abandoned Owyhee, IDWest May 2023
Solar project 704, Twin Falls County
Solar
330 MWWithdrawn / abandoned Twin Falls, IDWest Feb 2023target 2027
Solar + storage project C3-186, Blaine County
Solar + storage
300 MWWithdrawn / abandoned Blaine, IDWest May 2023target 2027
Onshore wind project C3-104, Bingham County
Onshore wind
300 MWWithdrawn / abandoned Bingham, IDWest May 2023target 2028
Solar + storage project C3-105, Bannock County
Solar + storage
300 MWWithdrawn / abandoned Bannock, IDWest May 2023target 2027
Solar + storage project G0967, Bonneville County
Solar + storage
300 MWWithdrawn / abandoned Bonneville, IDWest Oct 2023target 2027
Solar + storage project 711, Power County
Solar + storage
300 MWWithdrawn / abandoned Power, IDWest Apr 2023target 2027
Solar + storage project 703, Ada County
Solar + storage
250 MWWithdrawn / abandoned Ada, IDWest Feb 2023
Solar + storage project C3-108, Franklin County
Solar + storage
250 MWWithdrawn / abandoned Franklin, IDWest May 2023target 2027
Solar + storage project 720, Canyon County
Solar + storage
250 MWWithdrawn / abandoned Canyon, IDWest Jun 2023target 2027
Solar + storage project C3-112, Oneida County
Solar + storage
250 MWWithdrawn / abandoned Oneida, IDWest May 2023target 2027
Solar + storage project 728, Jerome County
Solar + storage
225 MWWithdrawn / abandoned Jerome, IDWest Jul 2023
Solar + storage project 700, Ada County
Solar + storage
200 MWWithdrawn / abandoned Ada, IDWest Jan 2023
Solar + storage project C3-109, Caribou County
Solar + storage
200 MWWithdrawn / abandoned Caribou, IDWest May 2023target 2027
Solar + storage project 699, Ada County
Solar + storage
200 MWWithdrawn / abandoned Ada, IDWest Jan 2023
Battery storage project C3-173, Jefferson County
Battery storage
200 MWWithdrawn / abandoned Jefferson, IDWest May 2023target 2027
Battery storage project C3-051, Franklin County
Battery storage ยท PacifiCorp
200 MWWithdrawn / abandoned Franklin, IDWest May 2023target 2030
Battery storage project C3-007, Owyhee County
Battery storage ยท PacifiCorp
200 MWWithdrawn / abandoned Owyhee, IDWest Apr 2023target 2029
Solar + storage project C3-183, Bingham County
Solar + storage
200 MWWithdrawn / abandoned Bingham, IDWest May 2023target 2028
Solar + storage project C3-099, Caribou County
Solar + storage
199 MWWithdrawn / abandoned Caribou, IDWest May 2023target 2027
Solar + storage project C3-037, Bannock County
Solar + storage
199 MWWithdrawn / abandoned Bannock, IDWest May 2023target 2027
Solar project C3-155, Bingham County
Solar ยท PacifiCorp
199 MWWithdrawn / abandoned Bingham, IDWest May 2023target 2028
Solar project C3-154, Bingham County
Solar ยท PacifiCorp
199 MWWithdrawn / abandoned Bingham, IDWest May 2023target 2028
Solar project C3-153, Bingham County
Solar ยท PacifiCorp
199 MWWithdrawn / abandoned Bingham, IDWest May 2023target 2028
Solar + storage project C3-159, Jefferson County
Solar + storage
199 MWWithdrawn / abandoned Jefferson, IDWest May 2023target 2026
Battery storage project C3-100, Bannock County
Battery storage
199 MWWithdrawn / abandoned Bannock, IDWest May 2023target 2027
Battery storage project C3-168, Owyhee County
Battery storage
175 MWWithdrawn / abandoned Owyhee, IDWest May 2023target 2026
Solar project G1033, Fremont County
Solar
170 MWWithdrawn / abandoned Fremont, IDWest Nov 2023target 2028
Solar project 743, Bingham County
Solar
150 MWWithdrawn / abandoned Bingham, IDWest Oct 2023target 2026
Solar project 713, Twin Falls County
Solar
150 MWWithdrawn / abandoned Twin Falls, IDWest May 2023target 2026
Solar project 742, Jerome County
Solar
150 MWWithdrawn / abandoned Jerome, IDWest Oct 2023target 2026
Solar + storage project 744, Jerome County
Solar + storage
150 MWWithdrawn / abandoned Jerome, IDWest Oct 2023target 2027
Battery storage project 731, Ada County
Battery storage
150 MWWithdrawn / abandoned Ada, IDWest Jul 2023target 2026
Battery storage project 705, Power County
Battery storage
130 MWWithdrawn / abandoned Power, IDWest Feb 2023target 2026
Solar project 741, Washington County
Solar
120 MWWithdrawn / abandoned Washington, IDWest Oct 2023target 2027
Solar project C3-156, Bingham County
Solar ยท PacifiCorp
100 MWWithdrawn / abandoned Bingham, IDWest May 2023target 2028
Battery storage project 709, Owyhee County
Battery storage
100 MWWithdrawn / abandoned Owyhee, IDWest Apr 2023target 2026
Battery storage project 745, Ada County
Battery storage
100 MWWithdrawn / abandoned Ada, IDWest Oct 2023target 2027
Battery storage project 722, Canyon County
Battery storage
100 MWWithdrawn / abandoned Canyon, IDWest Jun 2023target 2027
Solar project 715, Bingham County
Solar
100 MWWithdrawn / abandoned Bingham, IDWest May 2023target 2027
Solar project C3-157, Bingham County
Solar ยท PacifiCorp
100 MWWithdrawn / abandoned Bingham, IDWest May 2023target 2028
Wind + storage project 706, Elmore County
Wind + storage
100 MWWithdrawn / abandoned Elmore, IDWest Mar 2023target 2026
Battery storage project 721, Canyon County
Battery storage
100 MWWithdrawn / abandoned Canyon, IDWest Jun 2023target 2027
Battery storage project C3-172, Jefferson County
Battery storage
100 MWWithdrawn / abandoned Jefferson, IDWest May 2023target 2027
Solar + storage project C3-111, Caribou County
Solar + storage
95.0 MWWithdrawn / abandoned Caribou, IDWest May 2023target 2027
Solar project 729, Elmore County
Solar
70.0 MWWithdrawn / abandoned Elmore, IDWest Jul 2023
Onshore wind project G1006, Bonneville County
Onshore wind
43.0 MWWithdrawn / abandoned Bonneville, IDWest Nov 2023target 2025
Battery storage project 717, Owyhee County
Battery storage
24.0 MWWithdrawn / abandoned Owyhee, IDWest May 2023
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)