United States βΊ Grid βΊ Interconnection queues βΊ Idaho
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Idaho (2010 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project G0405, Madison County Onshore wind |
240 MW | Withdrawn / abandoned |
| Onshore wind project 315, Power County Onshore wind |
160 MW | Withdrawn / abandoned |
| Onshore wind project 28, Idaho County Onshore wind |
102 MW | Withdrawn / abandoned |
| Onshore wind project 327, Twin Falls County Onshore wind |
60.0 MW | Withdrawn / abandoned |
| Onshore wind project 321, Elmore County Onshore wind |
22.0 MW | Withdrawn / abandoned |
| Onshore wind project G0448, Cassia County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project G0443, Cassia County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 351, Owyhee County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project G0411, Cassia County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 346, Owyhee County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 355, Elmore County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Other project 335, Ada County Other |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 353, Blaine County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 354, Elmore County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Solar project 358, Owyhee County Solar |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 325, Twin Falls County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Solar project 356, Owyhee County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project 345, Owyhee County Solar |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 352, Blaine County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Other project 331, Elmore County Other |
20.0 MW | Withdrawn / abandoned |
| Solar project 342, Elmore County Solar |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 350, Twin Falls County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 323, Twin Falls County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project G0445, Cassia County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project G0412, Cassia County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 322, Twin Falls County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 324, Twin Falls County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 347, Owyhee County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project G0442, Cassia County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Other project 344, Ada County Other |
15.7 MW | Withdrawn / abandoned |
| Other project 322, Clark County Other |
15.6 MW | Withdrawn / abandoned |
| Onshore wind project 332, Elmore County Onshore wind |
15.0 MW | Withdrawn / abandoned |
| Onshore wind project 359, Lincoln County Onshore wind |
11.5 MW | Withdrawn / abandoned |
| Other project 315, Gem County Other |
10.0 MW | Withdrawn / abandoned |
| Onshore wind project 325, Bonneville County Onshore wind |
9.0 MW | Withdrawn / abandoned |
| Onshore wind project 349, Lincoln County Onshore wind |
6.5 MW | Withdrawn / abandoned |
| Gas project 29, Bonner County Gas |
6.0 MW | Withdrawn / abandoned |
| Onshore wind project 318, Owyhee County Onshore wind |
5.0 MW | Withdrawn / abandoned |
| Solar project 333, Elmore County Solar |
5.0 MW | Withdrawn / abandoned |
| Hydro project 344, Fremont County Hydro |
3.6 MW | Withdrawn / abandoned |
| Hydro project 330, Jerome County Hydro |
1.3 MW | Withdrawn / abandoned |
| Hydro project 360, Canyon County Hydro |
1.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)