πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Georgia

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Georgia (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6758 MW
Active in queue758 MW6 requests
Agreement signed758 MW6 requests
Withdrawn344,366 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-695, Sumter County
Solar
250 MWAgreement signed Sumter, GASoutheast May 2018target 2023
Solar project IC-696, Sumter County
Solar
250 MWAgreement signed Sumter, GASoutheast May 2018target 2023
Solar project IC-768, Dodge County
Solar
120 MWAgreement signed Dodge, GASoutheast Dec 2018target 2027
Solar project IC-769, Oglethorpe County
Solar
60.0 MWAgreement signed Oglethorpe, GASoutheast Dec 2018target 2023
Solar project IC-759, Burke County
Solar
40.0 MWAgreement signed Burke, GASoutheast Dec 2018target 2023
Solar project IC-762, Oglethorpe County
Solar
38.0 MWAgreement signed Oglethorpe, GASoutheast Dec 2018target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)