United States β€Ί Grid β€Ί Interconnection queues β€Ί Georgia

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Georgia (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4655 MW
Active in queue1,883 MW12 requests
Agreement signed708 MW5 requests
Withdrawn274,760 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Wadley Solar
Other
260 MWOperating Jefferson, GASoutheast Jul 20202024
SR Toombs
Solar
250 MWOperating Toombs, GASoutheast Apr 2020target 2024
CPV Stagecoach Solar
Solar
80.0 MWOperating Macon, GASoutheast Jul 20202024
GPC Mossy Branch Battery Storage Station
Battery storage
65.0 MWOperating Talbot, GASoutheast Apr 20202024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)