OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Florida (2021 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project 420, St Johns County Gas Β· Third Party |
744 MW | Withdrawn / abandoned |
| Gas project 82, Hillsborough County Gas |
186 MW | Withdrawn / abandoned |
| Solar project 80, Hillsborough County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 291, Wakulla County Solar Β· Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 78, Hillsborough County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 79, Hillsborough County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 294, Gilchrist County Solar Β· Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 81, Hillsborough County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 299, Manatee County Solar Β· Masked |
74.5 MW | Withdrawn / abandoned |
| Solar project 298, Manatee County Solar Β· Masked |
74.5 MW | Withdrawn / abandoned |
| Solar project 423, St. Lucie County Solar Β· FPL |
74.5 MW | Withdrawn / abandoned |
| Solar project 421, Baker County Solar Β· FPL |
14.5 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)