Projects with signed interconnection agreements in Florida (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2103 MW
Active in queue1,593 MW22 requests
Agreement signed103 MW2 requests
Withdrawn13921 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 76, Polk County
Solar
55.0 MWAgreement signed Polk, FLSoutheast Nov 2020target 2023
Other project 70, Polk County
Other
48.0 MWAgreement signed Polk, FLSoutheast May 2020target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)