United States β€Ί Grid β€Ί Interconnection queues β€Ί Delaware

OCTARY USA Β· INTERCONNECTION QUEUES

Solar interconnection queue in Delaware

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown11259 MW
Active in queue259 MW11 requests
Agreement signed50.0 MW3 requests
Withdrawn41995 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH1-672, Sussex County
Solar Β· TerraForm Freeman Solar, LLC
75.0 MWIn study Sussex, DEPJM Dec 2024
Cedar Creek Solar
Solar
20.0 MWPaused / redesign Kent, DEPJM Apr 2017target 2027
Cedar Creek Solar
Solar
20.0 MWPaused / redesign Kent, DEPJM Apr 2017target 2027
Raceway Solar
Solar
20.0 MWAgreement signed Kent, DEPJM Mar 2017target 2025
Solar project AG2-447, New Castle County
Solar Β· Freepoint Solar LLC
20.0 MWIn study New Castle, DEPJM Feb 2025target 2024
Raceway Solar
Solar
20.0 MWAgreement signed Kent, DEPJM Mar 2017target 2025
Cedar Creek Solar
Solar
19.8 MWPaused / redesign New Castle, DEPJM Oct 2016target 2027
Cedar Creek Solar
Solar
19.8 MWPaused / redesign New Castle, DEPJM Oct 2016target 2027
Cedar Creek Solar
Solar
18.8 MWPaused / redesign New Castle, DEPJM Oct 2016target 2027
Cedar Creek Solar
Solar
15.9 MWPaused / redesign New Castle, DEPJM Oct 2016target 2027
Raceway Solar
Solar
10.0 MWAgreement signed Kent, DEPJM Apr 2017target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)