United States β€Ί Grid β€Ί Interconnection queues β€Ί Connecticut

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Connecticut (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5142 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn72,851 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gravel Pit Solar
Solar
50.0 MWOperating Hartford, CTISO-NE Jun 2019target 2024
Millstone Increase
Nuclear
37.0 MWOperating New London, CTISO-NE Oct 2019target 2022
Gravel Pit Solar increase
Solar
25.0 MWOperating Hartford, CTISO-NE Dec 2019target 2024
NB Fuel Cell
Gas
20.2 MWOperating Hartford, CTISO-NE Nov 2019target 2024
Bloom Energy Fuel Cell
Other
10.2 MWOperating New London, CTISO-NE Aug 2019target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)