United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Colorado (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown336,512 MW
Active in queue400 MW2 requests
Agreement signed250 MW1 requests
Withdrawn336,512 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

33 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project GI-2018-30, Park County
Other
1,007 MWWithdrawn / abandoned Park, COWest Aug 2018target 2022
Onshore wind project GI-2018-5, Baca County
Onshore wind
700 MWWithdrawn / abandoned Baca, COWest Mar 2018target 2020
Onshore wind project GI-2018-4, Baca County
Onshore wind
700 MWWithdrawn / abandoned Baca, COWest Mar 2018target 2020
Onshore wind project GI-2018-26, Kit Carson County
Onshore wind
300 MWWithdrawn / abandoned Kit Carson, COWest Aug 2018target 2020
Onshore wind project GI-2018-22, Elbert County
Onshore wind
276 MWWithdrawn / abandoned Elbert, COWest May 2018target 2020
Solar project GI-2018-33, Pueblo County
Solar
240 MWWithdrawn / abandoned Pueblo, COWest Sep 2018target 2021
Solar project GI-2018-19, Pueblo County
Solar
230 MWWithdrawn / abandoned Pueblo, COWest Mar 2018target 2020
Solar project 18-02241, Weld County
Solar
220 MWWithdrawn / abandoned Weld, COWest Feb 2018target 2020
Solar project GI-2018-3, Weld County
Solar
220 MWWithdrawn / abandoned Weld, COWest Feb 2018target 2020
Solar project GI-2018-21, Weld County
Solar
220 MWWithdrawn / abandoned Weld, COWest May 2018target 2020
Onshore wind project GI-2018-27, Kit Carson County
Onshore wind
200 MWWithdrawn / abandoned Kit Carson, COWest Aug 2018target 2020
Battery storage project GEN-2018-030, Prowers County
Battery storage
200 MWWithdrawn / abandoned Prowers, COSPP May 2018target 2026
Solar project GI-2018-25, Pueblo County
Solar
200 MWWithdrawn / abandoned Pueblo, COWest Aug 2018target 2022
Solar project 18-05021, Weld County
Solar
150 MWWithdrawn / abandoned Weld, COWest May 2018target 2021
Solar + storage project GI-2018-1, Weld County
Solar + storage
150 MWWithdrawn / abandoned Weld, COWest Jan 2018target 2022
Solar project GI-2018-6, Pueblo County
Solar
150 MWWithdrawn / abandoned Pueblo, COWest Mar 2018target 2019
Solar project 18-09061, Larimer County
Solar
150 MWWithdrawn / abandoned Larimer, COWest Sep 2018target 2021
Solar + storage project 18-10101, Weld County
Solar + storage
120 MWWithdrawn / abandoned Weld, COWest Oct 2018target 2021
Solar + storage project GI-2018-29, Adams County
Solar + storage
110 MWWithdrawn / abandoned Adams, COWest Aug 2018target 2023
Onshore wind project 18-05102, Larimer County
Onshore wind
100 MWWithdrawn / abandoned Larimer, COWest May 2018target 2020
Battery storage project GI-2018-31, Boulder County
Battery storage
100 MWWithdrawn / abandoned Boulder, COWest Sep 2018target 2020
Battery storage project GI-2018-32, Boulder County
Battery storage
100 MWWithdrawn / abandoned Boulder, COWest Sep 2018target 2022
Onshore wind project 18-05101, Larimer County
Onshore wind
100 MWWithdrawn / abandoned Larimer, COWest May 2018target 2020
Solar project GI-2018-20, Weld County
Solar
80.0 MWWithdrawn / abandoned Weld, COWest May 2018target 2020
Onshore wind project 18-07261, Larimer County
Onshore wind
80.0 MWWithdrawn / abandoned Larimer, COWest Jul 2018target 2019
Solar project GI-2018-2, Weld County
Solar
80.0 MWWithdrawn / abandoned Weld, COWest Feb 2018target 2020
Solar project 18-02232, Weld County
Solar
80.0 MWWithdrawn / abandoned Weld, COWest Feb 2018target 2020
Solar project GI-2018-28, Pueblo County
Solar
74.9 MWWithdrawn / abandoned Pueblo, COWest Aug 2018target 2023
Solar project GI-2018-23, Park County
Solar
72.0 MWWithdrawn / abandoned Park, COWest Jul 2018target 2022
Solar project 18-04191, Weld County
Solar
30.0 MWWithdrawn / abandoned Weld, COWest Apr 2018target 2018
Solar project 18-02091, Larimer County
Solar
30.0 MWWithdrawn / abandoned Larimer, COWest Feb 2018target 2018
Onshore wind project 18-08021, Larimer County
Onshore wind
22.0 MWWithdrawn / abandoned Larimer, COWest Aug 2018target 2019
Solar project 18-02231, Larimer County
Solar
20.0 MWWithdrawn / abandoned Larimer, COWest Feb 2018target 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)