United States βΊ Grid βΊ Interconnection queues βΊ Colorado
SOLAR + STORAGE Β· WESTSolar + storage project GI-2018-1, Weld County
Solar + storage project GI-2018-1, Weld County is a 150 MW solar + storage request withdrawn in the West interconnection queue, in Weld County, Colorado, connecting to Public Service Company Of Colorado.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2018 (completed)
- Withdrawn / abandonedDec 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-2018-1
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company Of Colorado
- Connection point (POI)
- Green Valley 230 kV Substation
- Location
- Weld County, Colorado
- Technology
- Solar: 150 MW Β· Battery
- Total requested
- 150 MW
- Service type
- NRIS and ERIS
- Study phase
- Feasibility Study Underway Request Withdrawn 12/27/19
- Queue status
- Withdrawn
- Entered queue
- 12 January 2018
- Proposed online date
- December 2022
- Withdrawn
- December 2019
Location
Marker shows the centre of Weld County; the queue data does not give exact sites.
Other requests in Weld County
- Gas project GI-2007-11, Weld CountyGas Β· 380 MW Β· agreement signed
- Onshore wind project GI-2006-1i, Weld CountyOnshore wind Β· 300 MW Β· agreement signed
- Solar + storage project GI-DISIS-2022-02, Weld CountySolar + storage Β· 299 MW Β· agreement signed
- Solar + storage project GI-DISIS-2022-07, Weld CountySolar + storage Β· 299 MW Β· agreement signed
- Gas project GI-2006-1d, Weld CountyGas Β· 269 MW Β· agreement signed
- Onshore wind project GI-2007-6, Weld CountyOnshore wind Β· 200 MW Β· agreement signed
- Onshore wind project GI-2017-12, Weld CountyOnshore wind Β· 170 MW Β· agreement signed
- Gas project GI-2022-1, Weld CountyGas Β· 52.0 MW Β· agreement signed
- Onshore wind project GI-2007-5, Weld CountyOnshore wind Β· 50.0 MW Β· agreement signed
- Gas project GI-2021-2, Weld CountyGas Β· 49.0 MW Β· agreement signed
- Gas project GI-2021-3, Weld CountyGas Β· 35.0 MW Β· agreement signed
- Gas project GI-2020-05, Weld CountyGas Β· 24.0 MW Β· agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem