United States βΊ Grid βΊ Interconnection queues βΊ Colorado
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Colorado (2014 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project GEN-2014-015, Lincoln County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project GI-2014-10, Pueblo County Solar |
250 MW | Withdrawn / abandoned |
| Solar project BHCT G14, Pueblo County Solar |
120 MW | Withdrawn / abandoned |
| Solar project GI-2014-11, Alamosa County Solar |
100 MW | Withdrawn / abandoned |
| Onshore wind project GI-2014-1, Lincoln County Onshore wind |
100 MW | Withdrawn / abandoned |
| Solar project BHCT G13, Pueblo County Solar |
63.0 MW | Withdrawn / abandoned |
| Solar project GI-2014-8, Pueblo County Solar |
60.0 MW | Withdrawn / abandoned |
| Solar project BHCT-G12, Pueblo County Solar Β· Black Hills Electric Generation LLC |
60.0 MW | Withdrawn / abandoned |
| Solar project GI-2014-12, Pueblo County Solar |
53.0 MW | Withdrawn / abandoned |
| Solar project GI-2014-2, Alamosa County Solar |
35.0 MW | Withdrawn / abandoned |
| Other project GI-2014-3, Morgan County Other |
15.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)